Horizon Europe — RIA · 101099xxx (demo)
HELIOS-PV
High-Efficiency Lightweight Integrated Organic Solar Photovoltaics
Decisions & approvals
Approve publication: ‘F-07 absorber stability’ (TU Delft)
pendingConference paper for EU PVSEC 2027. Contains WP2 results with Fraunhofer encapsulation data.
Due 2026-11-28
| RISE | Elin Sandberg | awaiting | |
| Fraunhofer | Anna Keller | approved | 2026-10-23 — “OK — please cite D3.1.” |
| Solvia | Johan Lund | awaiting |
Shift D3.1 due date by 6 weeks
needs manual interpretationProposed internal re-plan following climate chamber maintenance. Requires assessment whether a formal amendment is needed.
Due 2026-11-05
The decision rule for this clause has not been reviewed and configured. Votes are recorded, but the coordinator must determine the outcome and whether a formal amendment is required.
| RISE | Elin Sandberg | awaiting | |
| Fraunhofer | Anna Keller | approved | 2026-10-20 |
Risk register
| Risk | Likelihood | Impact | Owner | Mitigation | Linked |
|---|---|---|---|---|---|
| Encapsulation test delay jeopardises MS3 | High | Medium | Fraunhofer | Book secondary chamber at RISE Borås. | D3.1 |
| Pilot equipment procurement lead time | Medium | High | Solvia | Parallel quotes from two vendors. | MS4 |
| Partner Energía Iberia not yet onboarded | Medium | Medium | RISE | Resend invitation; schedule call. | WP5 |