Horizon Europe — RIA · 101099xxx (demo)
HELIOS-PV
High-Efficiency Lightweight Integrated Organic Solar Photovoltaics
Open commitments
3
Due in 30 days
2
Overdue
2
Pending approvals
2
Report readiness
31%
Needs attention
- D3.1 Encapsulation test protocoloverdueFraunhofer · due 2026-10-10
- Provide signed partner material-transfer formsoverdueSolvia · due 2026-10-15 Manual entry · Elin Sandberg
- Approve publication: ‘F-07 absorber stability’ (TU Delft)pendingDecision due 2026-11-28
- Shift D3.1 due date by 6 weeksneeds manual interpretationDecision due 2026-11-05
AI briefing
Simulated · demo output
WP3 is the main schedule risk: D3.1 is 15 days overdue and MS3 depends on it. Solvia's update is stale (last confirmed 12 Sep) and blocked on material-transfer forms. One publication approval needs your vote before 28 Nov.
Briefings only draw on material you can access.
Work-package progress
WP1 Project management & coordination41%
WP2 Organic absorber materials62%
WP3 Encapsulation & durability38%
WP4 Pilot module manufacturing14%
WP5 Exploitation, dissemination & communication27%
Completion % is a self-reported proxy, not official acceptance by the granting authority.
Partner update freshness
- RISElast confirmed 2026-10-22
- TU Delftlast confirmed 2026-10-09
- Fraunhoferlast confirmed 2026-10-18
- Solvialast confirmed 2026-09-12
- Energía Iberianever confirmed
- PoliMinever confirmed
Upcoming milestones
MS1achieved
Consortium governance in place
2025-11-30
MS2achieved
Absorber candidates down-selected
2026-08-31
MS3planned
Encapsulation passes 1000 h damp-heat
2026-12-31
MS4planned
Pilot module ≥ 15% efficiency
2027-02-28